What is the Local Development Scheme (LDS)?

The Local Development Scheme (LDS) sets out the documents we will prepare as part of the Local Plan over the next 3 years.

Our LDS provides the community and other partners with information on the different Local Plan documents for the area, as well as the timescale, the associated work programmes, budgeting and resources required to produce each document.

The revised Local Development Scheme for the period 2017 - 2020 was agreed by the council's Cabinet on 17 October 2017. 

Local Development Scheme 2017-2020 (pdf 2.07mb opens in new window)

Please see below for the latest timetable for completing the various documents of the Local Plan.

What is the timescale for completing the Local Plan?

The latest timetable for each of the documents making up the Local Plan is set out below:

Strategy Document

Issues and Options – Complete 2008
Preferred Approach – Complete 2010
Further Consultation - Complete November-December 2011
Draft Strategy - Complete February - April 2013
Proposed Major Changes - Complete September 2013
Proposed Submission – Complete March 2014
Submission – April 2014
Independent Examination – Complete October-November 2014
Modifications consultation - March - May 2015
Inspector's report - received January 2016
Adoption – April 6 2016

Allocations Document

Potential Sites – Complete 2010
Draft Allocations - Complete February - April 2013
Proposed Major Changes - Complete September 2013
Proposed Submission – Complete March 2014
Submission – April 2014
Independent Examination – Complete October-November 2014
Modifications consultation - March - May 2015
Additional modification (Site SMB-B) - Jan-Feb 2016
Inspector's report - received June 2016
Adopted – July 27 2016

Bridlington Town Centre Area Action Plan

Issues and Options – Complete 2006
Preferred Options – Complete 2007
Second Preferred Options – Complete 2009
Publication – Complete 2010
Submission – Complete 2011
Independent Examination – Complete December 2011 and May 2012
Adopted – February 2013

Joint Minerals Plan

Issues and Options – Complete 2008
Preferred Approach – Complete 2010
Site Selection and Additional Sites - Complete early 2012
Second Preferred Approach - Summer 2016 
Publication – Expected Spring 2018
Submission – Expected Summer 2018 
Examination – Expected Summer 2018 
Adoption – Expected early 2019

Joint Waste Plan

Please see Hull City Council's website to see timescales for the Plan's preparation.

The Statement of Community Involvement and the Local Development Scheme have been completed. A number of Annual Monitoring Reports have also been prepared since 2005.

Last Updated: Monday, 09 July 2018